Planning & EstimatingCâu 506 / 700
A project must meet CALGreen construction waste requirements. What is the general contractor's BEST approach to demonstrate compliance during the job?
a.Divert a required minimum percentage of construction and demolition debris from landfill and keep documented records of recycling and reuse
b.Send all debris to the landfill and pay a fee
c.Burn scrap on site to reduce hauling
d.Assume the demolition sub handles it with no documentation
Giải thích
CALGreen requires diverting a minimum percentage of construction and demolition waste from landfills through recycling and reuse, supported by a waste management plan and documented receipts. Option a reflects this. Landfilling everything (b) fails the diversion target, on-site burning (c) is prohibited and unsafe, and undocumented reliance on a sub (d) leaves no proof of compliance for inspection.
Trích dẫn luật: 2025 California Green Building Standards Code (CALGreen)Luyện miễn phí toàn bộ 700 câu hỏi — không cần đăng ký.
Câu hỏi liên quan cùng chủ đề
- During a field inspection you notice the delivered floor joists are one size smaller than the joists specified on the approved structural plans. What is the BEST first step?
- A parking lot is 200 ft by 300 ft and will receive 3 inches of asphalt. Approximately how many cubic yards of compacted asphalt are needed?
- When performing a quantity takeoff from a set of plans, which practice BEST reduces costly estimating errors?
- A supplier quotes framing lumber at $650 per thousand board feet (MBF). A job requires 8,000 board feet. What is the estimated material cost before tax?
- A general contractor coordinates multiple subcontractors on a commercial project. Which practice BEST prevents schedule conflicts and duplicated work between trades?
- A room measures 14 ft by 16 ft with 9 ft high walls. You must apply two coats of paint to the walls only. Deducting one 3 ft x 7 ft door and two 3 ft x 4 ft windows, and assuming coverage of 350 sq ft per gallon per coat, what is the MINIMUM whole number of gallons to buy?
Cập nhật gần nhất: · quy trình kiểm tra
Đội Ngũ Biên Tập PrepPass · Đối chiếu với California CSLB General Building (B) Trade Examination · Quy trình kiểm tra