Planning & EstimatingCâu 503 / 700

During a field inspection you notice the delivered floor joists are one size smaller than the joists specified on the approved structural plans. What is the BEST first step?

a.Install them anyway to keep the schedule and note it later
b.Stop that installation and verify the discrepancy against the plans and structural engineer before proceeding
c.Cut the joists to fit and add extra nails
d.Order paint so finishes can start on schedule

Giải thích

A joist smaller than specified reduces load capacity and can be a life-safety defect. The BEST first step is to stop, verify the discrepancy against the approved plans, and consult the structural engineer before any framing is installed. Installing anyway (a) or field-modifying members (c) can compromise the structure and lead to failed inspections. Option d ignores the structural issue entirely.

Luyện miễn phí toàn bộ 700 câu hỏi — không cần đăng ký.

Câu hỏi liên quan cùng chủ đề

Cập nhật gần nhất: · quy trình kiểm tra

Đội Ngũ Biên Tập PrepPass · Đối chiếu với California CSLB General Building (B) Trade Examination · Quy trình kiểm tra
Báo lỗi