Planning & EstimatingCâu 500 / 700
You are preparing a critical path schedule. Which sequence of activities BEST reflects proper project coordination for a slab-on-grade building?
a.Frame walls, then pour footings, then run underground plumbing
b.Run underground plumbing, then pour the slab, then frame walls
c.Install roofing, then pour footings, then excavate
d.Paint interior, then set door frames, then rough electrical
Giải thích
Work must follow physical dependencies. Underground utilities are installed before the slab is poured, the slab is poured before walls are framed, and rough-in trades precede finishes. Option b follows that logic. Options a and c reverse dependent tasks (you cannot frame before the footing or roof before excavation), and option d puts paint before rough electrical, which forces demolition and rework.
Luyện miễn phí toàn bộ 700 câu hỏi — không cần đăng ký.
Câu hỏi liên quan cùng chủ đề
- A subcontractor submits shop drawings for structural steel connections. What is the general contractor's PRIMARY responsibility when reviewing them?
- The written specifications call for Type X gypsum board, but the plan detail simply notes '5/8 in drywall.' In the contract documents, how are such conflicts typically resolved?
- On a foundation inspection, you see anchor bolts set roughly 8 ft apart with the nearest bolt about 20 inches from the end of each sill plate section. Based on typical residential requirements, what is the MOST likely deficiency?
- A concrete slab is 30 ft by 40 ft and 4 inches thick. How many cubic yards of concrete are required?
- A bedroom plan shows a single egress window with a clear opening of 5.0 square feet and a sill 46 inches above the finished floor. Based on typical emergency escape requirements, what should the plan checker flag?
- During a field inspection you notice the delivered floor joists are one size smaller than the joists specified on the approved structural plans. What is the BEST first step?
Cập nhật gần nhất: · quy trình kiểm tra
Đội Ngũ Biên Tập PrepPass · Đối chiếu với California CSLB General Building (B) Trade Examination · Quy trình kiểm tra