Planning & EstimatingCâu 500 / 700

You are preparing a critical path schedule. Which sequence of activities BEST reflects proper project coordination for a slab-on-grade building?

a.Frame walls, then pour footings, then run underground plumbing
b.Run underground plumbing, then pour the slab, then frame walls
c.Install roofing, then pour footings, then excavate
d.Paint interior, then set door frames, then rough electrical

Giải thích

Work must follow physical dependencies. Underground utilities are installed before the slab is poured, the slab is poured before walls are framed, and rough-in trades precede finishes. Option b follows that logic. Options a and c reverse dependent tasks (you cannot frame before the footing or roof before excavation), and option d puts paint before rough electrical, which forces demolition and rework.

Luyện miễn phí toàn bộ 700 câu hỏi — không cần đăng ký.

Câu hỏi liên quan cùng chủ đề

Cập nhật gần nhất: · quy trình kiểm tra

Đội Ngũ Biên Tập PrepPass · Đối chiếu với California CSLB General Building (B) Trade Examination · Quy trình kiểm tra
Báo lỗi