Planning & EstimatingCâu 498 / 700

The written specifications call for Type X gypsum board, but the plan detail simply notes '5/8 in drywall.' In the contract documents, how are such conflicts typically resolved?

a.The specifications generally govern over the drawings for material quality, but the contractor should seek written clarification
b.The drawings always override the specifications
c.The lowest-cost interpretation automatically applies
d.Whatever the crew installs first becomes the standard

Giải thích

When drawings and specifications conflict, the specifications typically govern for materials and quality of work, while drawings govern for dimensions and location; however, the BEST practice is to request a written clarification or RFI so intent is documented. Options b and c are false generalizations, and option d ignores the contract hierarchy and invites disputes and rework.

Luyện miễn phí toàn bộ 700 câu hỏi — không cần đăng ký.

Câu hỏi liên quan cùng chủ đề

Cập nhật gần nhất: · quy trình kiểm tra

Đội Ngũ Biên Tập PrepPass · Đối chiếu với California CSLB General Building (B) Trade Examination · Quy trình kiểm tra
Báo lỗi