Planning & EstimatingCâu 497 / 700
A subcontractor submits shop drawings for structural steel connections. What is the general contractor's PRIMARY responsibility when reviewing them?
a.To redesign the connections to save steel
b.To approve them immediately so fabrication is not delayed
c.To ignore them because the engineer already stamped the plans
d.To check them for conformance with the design intent and coordinate them with other trades before the engineer of record reviews
Giải thích
Shop drawings translate the design documents into fabrication and installation detail. The general contractor reviews them for conformance with the design intent and coordination with other trades, then forwards them to the engineer of record for final review. The GC does not redesign the structure (a), rush unchecked approvals (b), or skip review (c). Proper shop drawing review prevents costly field conflicts.
Luyện miễn phí toàn bộ 700 câu hỏi — không cần đăng ký.
Câu hỏi liên quan cùng chủ đề
- Direct costs on a job are $12,000 in materials and $8,000 in labor. If you add 15 percent for overhead and profit, what is the total bid price?
- A concrete block wall is 8 ft high and 40 ft long, built with standard 8 in by 16 in nominal units. Using the rule of 1.125 blocks per square foot of wall face, how many blocks are needed (before waste)?
- A framing plan shows interior stairs with 8.5 inch risers and 9 inch treads. Compared with typical residential code limits, what is the MOST likely problem an estimator or inspector should flag?
- The written specifications call for Type X gypsum board, but the plan detail simply notes '5/8 in drywall.' In the contract documents, how are such conflicts typically resolved?
- On a foundation inspection, you see anchor bolts set roughly 8 ft apart with the nearest bolt about 20 inches from the end of each sill plate section. Based on typical residential requirements, what is the MOST likely deficiency?
- You are preparing a critical path schedule. Which sequence of activities BEST reflects proper project coordination for a slab-on-grade building?
Cập nhật gần nhất: · quy trình kiểm tra
Đội Ngũ Biên Tập PrepPass · Đối chiếu với California CSLB General Building (B) Trade Examination · Quy trình kiểm tra