Planning & EstimatingCâu 535 / 700
A gravel base 40 ft by 60 ft is placed 6 inches thick. If compacted gravel weighs about 100 pounds per cubic foot, approximately how many tons are required?
a.30 tons
b.60 tons
c.45 tons
d.90 tons
Giải thích
Volume = 40 x 60 x 0.5 ft (6 in) = 1,200 cubic feet. Weight = 1,200 x 100 = 120,000 pounds. Tons = 120,000 / 2,000 = 60 tons. Option a uses the wrong thickness or halves the result. Options c and d misapply the density. Convert depth to feet, find cubic feet, multiply by density, then divide by 2,000 pounds per ton.
Luyện miễn phí toàn bộ 700 câu hỏi — không cần đăng ký.
Câu hỏi liên quan cùng chủ đề
- A room is 12 ft by 20 ft with 8 ft ceilings. You will hang 4 ft by 8 ft gypsum board on all four walls and the ceiling, ignoring openings and waste. What is the MINIMUM number of full sheets needed?
- A gable roof has a total span of 24 ft and a slope of 6 in 12 (a 6-inch rise for every 12 inches of run). Ignoring overhang, what is the approximate theoretical length of a common rafter from ridge to top plate?
- An interior stair must connect two floors with a total floor-to-floor height of 108 inches. If the code limits each riser to a MAXIMUM of 7.75 inches, what is the MINIMUM number of risers required?
- Your total job cost is $18,000 and you want a 25 percent gross profit MARGIN on the selling price. What is the correct selling price?
- A crew must install 1,500 square feet of flooring at a production rate of 50 square feet per labor-hour. What is the MINIMUM total labor-hours the estimate should include for this task?
- A concrete sidewalk is 4 ft wide, 75 ft long, and 4 inches thick. Ignoring waste, approximately how many cubic yards of concrete are needed?
Cập nhật gần nhất: · quy trình kiểm tra
Đội Ngũ Biên Tập PrepPass · Đối chiếu với California CSLB General Building (B) Trade Examination · Quy trình kiểm tra