Planning & EstimatingCâu 537 / 700
A crew must install 1,500 square feet of flooring at a production rate of 50 square feet per labor-hour. What is the MINIMUM total labor-hours the estimate should include for this task?
a.15 labor-hours
b.30 labor-hours
c.60 labor-hours
d.75 labor-hours
Giải thích
Labor-hours = area divided by production rate = 1,500 / 50 = 30 labor-hours. This is total effort regardless of crew size; a 2-worker crew would finish in about 15 clock hours, but the labor-hour count is still 30. Option a confuses clock hours with labor-hours. Options c and d misapply the rate. Divide the quantity by the output per labor-hour to size the labor line.
Luyện miễn phí toàn bộ 700 câu hỏi — không cần đăng ký.
Câu hỏi liên quan cùng chủ đề
- An interior stair must connect two floors with a total floor-to-floor height of 108 inches. If the code limits each riser to a MAXIMUM of 7.75 inches, what is the MINIMUM number of risers required?
- A gravel base 40 ft by 60 ft is placed 6 inches thick. If compacted gravel weighs about 100 pounds per cubic foot, approximately how many tons are required?
- Your total job cost is $18,000 and you want a 25 percent gross profit MARGIN on the selling price. What is the correct selling price?
- A concrete sidewalk is 4 ft wide, 75 ft long, and 4 inches thick. Ignoring waste, approximately how many cubic yards of concrete are needed?
- A straight fence run is 240 ft long with posts spaced 8 ft on center. Counting both end posts, what is the MINIMUM number of posts required?
- A slab is 24 ft wide. Reinforcing bars run in one direction spaced 12 inches on center, with a bar at each edge. What is the MINIMUM number of bars in that direction?
Cập nhật gần nhất: · quy trình kiểm tra
Đội Ngũ Biên Tập PrepPass · Đối chiếu với California CSLB General Building (B) Trade Examination · Quy trình kiểm tra