Planning & EstimatingCâu 538 / 700
A concrete sidewalk is 4 ft wide, 75 ft long, and 4 inches thick. Ignoring waste, approximately how many cubic yards of concrete are needed?
a.About 3.7 cubic yards
b.About 1.9 cubic yards
c.About 11.1 cubic yards
d.About 7.4 cubic yards
Giải thích
Convert thickness: 4 in = 0.333 ft. Volume = 4 x 75 x 0.333 = about 100 cubic feet. Cubic yards = 100 / 27 = 3.70. Option b halves the value. Option c wrongly treats the thickness as feet. Option d doubles the result. Always convert inches to feet, compute cubic feet, then divide by 27.
Luyện miễn phí toàn bộ 700 câu hỏi — không cần đăng ký.
Câu hỏi liên quan cùng chủ đề
- A gravel base 40 ft by 60 ft is placed 6 inches thick. If compacted gravel weighs about 100 pounds per cubic foot, approximately how many tons are required?
- Your total job cost is $18,000 and you want a 25 percent gross profit MARGIN on the selling price. What is the correct selling price?
- A crew must install 1,500 square feet of flooring at a production rate of 50 square feet per labor-hour. What is the MINIMUM total labor-hours the estimate should include for this task?
- A straight fence run is 240 ft long with posts spaced 8 ft on center. Counting both end posts, what is the MINIMUM number of posts required?
- A slab is 24 ft wide. Reinforcing bars run in one direction spaced 12 inches on center, with a bar at each edge. What is the MINIMUM number of bars in that direction?
- During plan review of a finished basement, you notice a proposed habitable rec room with a ceiling height of 6 ft 10 in. What is the BEST conclusion?
Cập nhật gần nhất: · quy trình kiểm tra
Đội Ngũ Biên Tập PrepPass · Đối chiếu với California CSLB General Building (B) Trade Examination · Quy trình kiểm tra