Planning & EstimatingCâu 581 / 700
A set of 6 identical spread (pad) footings is shown, each 3 ft by 3 ft in plan and 12 in deep. What is the MINIMUM volume of concrete required for all six?
a.2.0 cubic yards
b.54 cubic yards
c.6.0 cubic yards
d.0.33 cubic yards
Giải thích
Each footing is 3 ft x 3 ft x 1 ft = 9 cubic feet. Six footings = 54 cubic feet. Divide by 27 to convert to cubic yards: 54 / 27 = 2.0 cubic yards (a). Option (b) leaves the answer in cubic feet without dividing by 27. Option (c) confuses the footing count with cubic yards. Option (d) is the volume of a single footing (9 / 27 = 0.33) rather than all six.
Luyện miễn phí toàn bộ 700 câu hỏi — không cần đăng ký.
Câu hỏi liên quan cùng chủ đề
- Near the end of a project, the owner and architect walk the building and create a list of incomplete or defective items to be corrected before final payment. What is this document BEST called?
- On a new residential project subject to CALGreen, a submitted showerhead is rated at 2.5 gallons per minute. What is the BEST assessment of water-efficiency compliance?
- During a pre-pour inspection of a footing formed directly against earth, you check the reinforcing steel. Which condition is MOST important to verify before concrete is placed?
- A round drilled pier is 24 inches in diameter and 18 ft deep. Using pi = 3.1416, what is the APPROXIMATE volume of concrete required to fill it?
- A concrete stem wall is 10 inches thick, 3 ft tall, and 80 ft long. How many cubic yards of concrete are required?
- A solid concrete stair has 4 steps, each with a 7-inch rise and a 12-inch run, and is 4 ft wide. Treating the cross-section as stacked steps (area = rise x run x N(N+1)/2), what is the APPROXIMATE concrete volume?
Cập nhật gần nhất: · quy trình kiểm tra
Đội Ngũ Biên Tập PrepPass · Đối chiếu với California CSLB General Building (B) Trade Examination · Quy trình kiểm tra