Near the end of a project, the owner and architect walk the building and create a list of incomplete or defective items to be corrected before final payment. What is this document BEST called?
a.A punch list
b.A submittal log
c.A bid addendum
d.A daily report
Giải thích
A punch list is the itemized list of remaining or deficient work identified at substantial completion that must be finished before final acceptance and payment. A submittal log tracks product approvals. A bid addendum revises documents during bidding. A daily report records site activity. Managing the punch list efficiently is key to closing out and getting paid.
Luyện miễn phí toàn bộ 700 câu hỏi — không cần đăng ký.
Câu hỏi liên quan cùng chủ đề
- The specifications name a specific product but add the phrase 'or equal.' A subcontractor wants to use a different brand. What is the BEST procedure?
- Before forwarding a fabricator's shop drawings to the architect, what is the general contractor's PRIMARY responsibility?
- Before starting sitework, the crew needs a consistent reference for all elevations across the project. Which practice BEST establishes this?
- On a new residential project subject to CALGreen, a submitted showerhead is rated at 2.5 gallons per minute. What is the BEST assessment of water-efficiency compliance?
- During a pre-pour inspection of a footing formed directly against earth, you check the reinforcing steel. Which condition is MOST important to verify before concrete is placed?
- A set of 6 identical spread (pad) footings is shown, each 3 ft by 3 ft in plan and 12 in deep. What is the MINIMUM volume of concrete required for all six?
Cập nhật gần nhất: · quy trình kiểm tra
Đội Ngũ Biên Tập PrepPass · Đối chiếu với California CSLB General Building (B) Trade Examination · Quy trình kiểm tra