Planning & EstimatingCâu 553 / 700

Near the end of a project, the owner and architect walk the building and create a list of incomplete or defective items to be corrected before final payment. What is this document BEST called?

a.A punch list
b.A submittal log
c.A bid addendum
d.A daily report

Giải thích

A punch list is the itemized list of remaining or deficient work identified at substantial completion that must be finished before final acceptance and payment. A submittal log tracks product approvals. A bid addendum revises documents during bidding. A daily report records site activity. Managing the punch list efficiently is key to closing out and getting paid.

Luyện miễn phí toàn bộ 700 câu hỏi — không cần đăng ký.

Câu hỏi liên quan cùng chủ đề

Cập nhật gần nhất: · quy trình kiểm tra

Đội Ngũ Biên Tập PrepPass · Đối chiếu với California CSLB General Building (B) Trade Examination · Quy trình kiểm tra
Báo lỗi