Planning & EstimatingCâu 552 / 700
Before starting sitework, the crew needs a consistent reference for all elevations across the project. Which practice BEST establishes this?
a.Measure heights from the top of the nearest fence each day
b.Use the finished floor of an adjacent building without verification
c.Estimate grades by eye and adjust later
d.Set a fixed benchmark and reference all elevations to that datum
Giải thích
Establishing a permanent, protected benchmark and referencing every elevation to that single datum ensures footings, slabs, and drainage tie together accurately. Option a uses an unstable reference that can move. Option b assumes an unverified elevation. Option c invites cumulative error. A common datum prevents mismatched grades and costly rework.
Luyện miễn phí toàn bộ 700 câu hỏi — không cần đăng ký.
Câu hỏi liên quan cùng chủ đề
- Two days before bids are due, the architect issues a document that changes the window schedule for all bidders. What is this document BEST called?
- The specifications name a specific product but add the phrase 'or equal.' A subcontractor wants to use a different brand. What is the BEST procedure?
- Before forwarding a fabricator's shop drawings to the architect, what is the general contractor's PRIMARY responsibility?
- Near the end of a project, the owner and architect walk the building and create a list of incomplete or defective items to be corrected before final payment. What is this document BEST called?
- On a new residential project subject to CALGreen, a submitted showerhead is rated at 2.5 gallons per minute. What is the BEST assessment of water-efficiency compliance?
- During a pre-pour inspection of a footing formed directly against earth, you check the reinforcing steel. Which condition is MOST important to verify before concrete is placed?
Cập nhật gần nhất: · quy trình kiểm tra
Đội Ngũ Biên Tập PrepPass · Đối chiếu với California CSLB General Building (B) Trade Examination · Quy trình kiểm tra