Planning & EstimatingCâu 550 / 700

The specifications name a specific product but add the phrase 'or equal.' A subcontractor wants to use a different brand. What is the BEST procedure?

a.Install the substitute immediately since 'or equal' allows any brand
b.Ignore the phrase and only the named product is permitted
c.Submit the proposed product for the design professional's approval before ordering
d.Let the supplier decide which product is equal

Giải thích

An 'or equal' clause permits substitutions, but the burden is on the contractor to demonstrate the proposed item meets the specified performance, and the design professional must approve it before it is ordered or installed. Option a skips required approval. Option b ignores the clause. Option d improperly delegates a design judgment to a vendor. Route substitutions through the submittal and approval process.

Luyện miễn phí toàn bộ 700 câu hỏi — không cần đăng ký.

Câu hỏi liên quan cùng chủ đề

Cập nhật gần nhất: · quy trình kiểm tra

Đội Ngũ Biên Tập PrepPass · Đối chiếu với California CSLB General Building (B) Trade Examination · Quy trình kiểm tra
Báo lỗi