Two days before bids are due, the architect issues a document that changes the window schedule for all bidders. What is this document BEST called?
a.An addendum
b.A change order
c.A submittal
d.A punch list
Giải thích
A revision issued during the bidding period, before any contract is signed, is an addendum, and it becomes part of the contract documents. A change order modifies an already-executed contract during construction. A submittal is contractor-provided product data for approval. A punch list records incomplete or corrective items near completion. Recognizing the correct instrument ensures the bid reflects the latest scope.
Luyện miễn phí toàn bộ 700 câu hỏi — không cần đăng ký.
Câu hỏi liên quan cùng chủ đề
- A plan provides an attic access hatch of 20 in by 28 in for an attic that is over 30 square feet with more than 30 inches of headroom. What is the BEST correction?
- A 1,800-square-foot crawl space uses standard (non-vapor-barrier) under-floor ventilation openings. Using the common 1-to-150 ratio, what is the MINIMUM net ventilation area required?
- During construction you find the architectural drawings show a beam at one size but the structural drawings show a larger size for the same beam. What is the BEST first action?
- The specifications name a specific product but add the phrase 'or equal.' A subcontractor wants to use a different brand. What is the BEST procedure?
- Before forwarding a fabricator's shop drawings to the architect, what is the general contractor's PRIMARY responsibility?
- Before starting sitework, the crew needs a consistent reference for all elevations across the project. Which practice BEST establishes this?
Cập nhật gần nhất: · quy trình kiểm tra
Đội Ngũ Biên Tập PrepPass · Đối chiếu với California CSLB General Building (B) Trade Examination · Quy trình kiểm tra