Before forwarding a fabricator's shop drawings to the architect, what is the general contractor's PRIMARY responsibility?

a.Redesign the connections to reduce cost
b.Review and coordinate the drawings with field conditions and other trades, then stamp them
c.Forward them unopened to save time
d.Approve them on the architect's behalf

Giải thích

The GC must review and coordinate shop drawings against field dimensions and adjacent work, and stamp or note that review, before transmitting them to the design professional for final approval. Option a oversteps into design. Option c skips the required coordination that catches conflicts early. Option d usurps the architect's approval authority. The GC's review is a quality-control checkpoint, not final design approval.

Luyện miễn phí toàn bộ 700 câu hỏi — không cần đăng ký.

Câu hỏi liên quan cùng chủ đề

Cập nhật gần nhất: · quy trình kiểm tra

Đội Ngũ Biên Tập PrepPass · Đối chiếu với California CSLB General Building (B) Trade Examination · Quy trình kiểm tra
Báo lỗi