Planning & EstimatingCâu 614 / 700
In construction estimating, which BEST describes the difference between fixed and variable overhead?
a.Fixed overhead changes with each job's size, while variable overhead stays constant all year.
b.Both fixed and variable overhead are direct job costs charged to a single project.
c.Fixed overhead is the profit, and variable overhead is the labor burden.
d.Fixed overhead (e.g., office rent, insurance, licenses) continues regardless of how much work you do, while variable overhead rises and falls with the volume of work.
Giải thích
Correct: fixed overhead is relatively constant no matter the workload (rent, insurance, base salaries), while variable overhead scales with activity (temporary office help, added equipment). The first option reverses the two behaviors. Overhead is an indirect cost, not a direct job cost, so the second option is wrong. Overhead is not profit and not simply labor burden, so the third option is wrong.
Luyện miễn phí toàn bộ 700 câu hỏi — không cần đăng ký.
Câu hỏi liên quan cùng chủ đề
- Two contractors discuss pricing. What is the correct distinction between 'markup' and 'gross margin'?
- A job costs $16,000 and is sold for $20,000. What is the gross MARGIN percentage on the selling price?
- Your direct cost on a job is $9,000. You apply a 30 percent markup ON COST. What is the selling price?
- A contractor's annual overhead is $120,000 and expects about $600,000 in direct job costs for the year. To recover overhead evenly, approximately what percentage should be added to each job's direct cost for overhead?
- On a lump-sum project, what is the PRIMARY purpose of the schedule of values?
- A progress payment application shows $80,000 of work completed this period. The contract allows 10 percent retention. How much should the owner PAY for this period after retention is withheld?
Cập nhật gần nhất: · quy trình kiểm tra
Đội Ngũ Biên Tập PrepPass · Đối chiếu với California CSLB General Building (B) Trade Examination · Quy trình kiểm tra