Planning & EstimatingCâu 616 / 700
On a lump-sum project, what is the PRIMARY purpose of the schedule of values?
a.It breaks the total contract price into line-item values so that progress payments can be measured against the work actually completed.
b.It lists every subcontractor's bid bond amount.
c.It is the closeout list of defective items to correct before final payment.
d.It records attendance at weekly safety meetings.
Giải thích
Correct: the schedule of values allocates the lump-sum contract price among the components of the work, giving a basis to evaluate each progress payment against percentage complete. Bid bond amounts belong on bond forms, not the schedule of values. The closeout defect list is the punch list. Safety attendance is a separate record.
Luyện miễn phí toàn bộ 700 câu hỏi — không cần đăng ký.
Câu hỏi liên quan cùng chủ đề
- Your direct cost on a job is $9,000. You apply a 30 percent markup ON COST. What is the selling price?
- In construction estimating, which BEST describes the difference between fixed and variable overhead?
- A contractor's annual overhead is $120,000 and expects about $600,000 in direct job costs for the year. To recover overhead evenly, approximately what percentage should be added to each job's direct cost for overhead?
- A progress payment application shows $80,000 of work completed this period. The contract allows 10 percent retention. How much should the owner PAY for this period after retention is withheld?
- A grading and utility project has uncertain quantities of rock excavation that cannot be measured accurately until digging begins. Which contract type is BEST suited?
- When is a cost-plus-fee contract MOST appropriate?