Planning & EstimatingCâu 625 / 700
What typically triggers a change order, and how is it documented?
a.A change in scope, an owner-directed modification, or unforeseen conditions triggers it; it is a written, signed amendment adjusting the contract price and/or time.
b.Any RFI automatically becomes a change order the moment it is answered.
c.It is a document issued to all bidders before bids are due to modify the scope.
d.It is the contractor's internal cost estimate and needs no owner signature.
Giải thích
Correct: a change order is a formal written modification, signed by the parties, that adjusts price and/or schedule when the scope changes, the owner directs a change, or conditions differ from those shown. An RFI only clarifies documents and does not by itself change the contract. A pre-bid modification is an addendum, not a change order. A change order requires the owner's signature, not just an internal estimate.
Luyện miễn phí toàn bộ 700 câu hỏi — không cần đăng ký.
Câu hỏi liên quan cùng chủ đề
- On a bonded public project, what is the distinction between a performance bond and a payment bond?
- On a California public-works project above the applicable threshold, what does the law generally require regarding wages and records?
- What is the PRIMARY purpose of value engineering on a construction project?
- When should a contractor issue a Request for Information (RFI)?
- Which statement BEST distinguishes shop drawings, product data, and samples as types of submittals?
- Under CSI MasterFormat, cast-in-place structural concrete work is specified under which division?
Cập nhật gần nhất: · quy trình kiểm tra
Đội Ngũ Biên Tập PrepPass · Đối chiếu với California CSLB General Building (B) Trade Examination · Quy trình kiểm tra