When should a contractor issue a Request for Information (RFI)?
a.To formally bill the owner for work completed during the pay period.
b.To obtain clarification from the design team when the contract documents are unclear, incomplete, or appear to conflict.
c.To notify field workers about the time and place of a safety meeting.
d.To request early release of retention before completion.
Giải thích
Correct: an RFI is the formal channel to ask the architect/engineer to clarify or resolve ambiguities, gaps, or conflicts in the drawings and specifications before proceeding. Billing is done through a payment application, not an RFI. Safety notices and retention requests are unrelated to the RFI process.
Luyện miễn phí toàn bộ 700 câu hỏi — không cần đăng ký.
Câu hỏi liên quan cùng chủ đề
- On a California public-works project above the applicable threshold, what does the law generally require regarding wages and records?
- What is the PRIMARY purpose of value engineering on a construction project?
- What typically triggers a change order, and how is it documented?
- Which statement BEST distinguishes shop drawings, product data, and samples as types of submittals?
- Under CSI MasterFormat, cast-in-place structural concrete work is specified under which division?
- Under CSI MasterFormat, concrete masonry unit (CMU) and brick work fall under which division?
Cập nhật gần nhất: · quy trình kiểm tra
Đội Ngũ Biên Tập PrepPass · Đối chiếu với California CSLB General Building (B) Trade Examination · Quy trình kiểm tra