Dịch vụ & Phân phốiCâu 108 / 521
A separately derived system (such as the secondary of a transformer feeding a distribution panel) must have a system bonding jumper connecting:
a.The two ungrounded phases together
b.The grounded conductor to the supply-side bonding jumper and equipment grounding conductor at the source or first disconnect
c.The neutral to a branch-circuit breaker
d.Only the metal raceway to earth
Giải thích
Per 250.30(A), a separately derived system requires a system bonding jumper connecting the grounded conductor to the supply-side bonding jumper and/or equipment grounding conductor at a single point (at the source or the first disconnect). Bonding phases together or omitting the grounded conductor connection would not establish the required fault path.
Trích dẫn luật: 2023 NEC §250.30Luyện miễn phí toàn bộ 521 câu hỏi — không cần đăng ký.
Câu hỏi liên quan cùng chủ đề
- For a 200 A service where the equipment and conductors are all rated for it, the conductor ampacity used for termination sizing is normally based on which temperature column?
- A panelboard must have a rating (busbar ampacity) not less than:
- Service-entrance conductors installed in a raceway in a wet location (such as underground or exposed to weather) must be:
- A detached garage is supplied by a feeder from the main dwelling. At the garage, the code generally requires:
- On a 4-wire delta system where the midpoint of one phase is grounded, the conductor with the higher voltage to ground (the high leg) must be durably and permanently marked, typically colored:
- A service raceway enters a building from an underground distribution system. To prevent moisture and gases from entering, the raceway must be:
Cập nhật gần nhất: · quy trình kiểm tra