Thoát nước, Nước thải & Thông hơiCâu 133 / 360
A tall drainage stack with five or more branch intervals generally requires what to protect trap seals from pressure changes?
a.A vent stack (main vent) installed adjacent to the soil/waste stack
b.An additional cleanout only
c.A larger building trap
d.A backwater valve at each branch
Giải thích
A vent stack, or main vent, runs parallel to a tall soil or waste stack and is cross-connected with relief vents at intervals. It equalizes air pressure so that the surge of water down the stack does not siphon or blow out trap seals. Vent stacks are typically required once a stack has several branch intervals.
Trích dẫn luật: 2022 California Plumbing Code (CPC) §904.0Luyện miễn phí toàn bộ 360 câu hỏi — không cần đăng ký.
Câu hỏi liên quan cùng chủ đề
- A circuit vent serving a battery of floor-mounted fixtures on a horizontal branch may serve a maximum of how many fixtures?
- A kitchen island sink with no adjacent wall for a conventional vent is best served by which venting arrangement?
- What is the minimum diameter permitted for a vent pipe, regardless of the fixture it serves?
- In a cold climate subject to frost closure, a vent through the roof must be enlarged to a minimum of 3 inches. Where must that increase in size be made?
- A sewage ejector receiving the discharge of a water closet must have a discharge pipe of not less than what diameter and be able to pass a 2-inch solid?
- A sump or receiving tank that collects sewage from fixtures located below the sewer level must be…
Cập nhật gần nhất: · quy trình kiểm tra
Đội Ngũ Biên Tập PrepPass · Đối chiếu với California CSLB C-36 Plumbing Trade Examination · Quy trình kiểm tra