Lập kế hoạch & Dự toánCâu 278 / 360
When planning backfill over a drainage pipe laid in a trench, what is the correct practice under the CPC?
a.Dump large rocks directly on the pipe to save fill
b.Leave the pipe unsupported and backfill only the ends
c.Support the pipe on firm bedding for its full length and place backfill so the pipe is not damaged or displaced
d.Backfill only after the final inspection is passed
Giải thích
CPC 314.0 requires piping to be supported on undisturbed or well-compacted material for its full length, with backfill placed in a way that does not damage or move the pipe. Rocks or point loads can crack pipe or create bellies. Proper trench and bedding planning protects the line and preserves the required slope.
Trích dẫn luật: CPC 314.0Luyện miễn phí toàn bộ 360 câu hỏi — không cần đăng ký.
Câu hỏi liên quan cùng chủ đề
- You are doing a material takeoff from an isometric of a bathroom group. The riser drops through one floor and makes three horizontal offsets, each requiring a pair of 90° bends. How many 90° elbows should you count for those offsets alone?
- You are laying out a 2-inch horizontal drainage pipe. What minimum slope does the CPC require for a pipe this size?
- When planning cleanout locations on a long horizontal building drain, what is the maximum spacing between cleanouts under the CPC?
- In estimating, a "labor unit" for a plumbing task usually represents what?
- On a plumbing riser diagram, what does the drawing primarily show?
- A plan symbol showing a small circle with a bisecting line and the note "FD" most likely indicates what?
Cập nhật gần nhất: · quy trình kiểm tra
Đội Ngũ Biên Tập PrepPass · Đối chiếu với California CSLB C-36 Plumbing Trade Examination · Quy trình kiểm tra