Lập kế hoạch & Dự toánCâu 288 / 360
While laying out the building drain you reach a 90° change of direction. Under the CPC, what feature is generally required at such a change of direction on the horizontal drain?
a.A cleanout
b.A pressure-reducing valve
c.A backwater vent only
d.An expansion tank
Giải thích
CPC 707.0 requires cleanouts at changes of direction greater than 45 degrees in horizontal drainage piping so the line can be rodded from that point. Planning the cleanout into the layout keeps the run serviceable. Missing a required cleanout is a common cause of failed rough-in inspections.
Trích dẫn luật: CPC 707.0Luyện miễn phí toàn bộ 360 câu hỏi — không cần đăng ký.
Câu hỏi liên quan cùng chủ đề
- In estimating pipe for a run, why do experienced estimators add a waste/scrap allowance to the measured length?
- On the plans a valve symbol drawn as two triangles meeting point-to-point (a bowtie) most commonly represents which device?
- A restaurant plan calls for eight identical mop-sink rough-ins. Each rough-in needs 1 P-trap, 1 trap adapter, and 2 drop-ear elbows. How many drop-ear elbows go on the takeoff?
- What is the main purpose of a plumbing fixture schedule on a set of plans?
- When sizing the water distribution system for a building, which CPC-recognized method bases pipe sizes on total demand expressed in water supply fixture units and available pressure?
- You must coordinate a 4-inch sanitary line and an HVAC duct that cross in a tight ceiling. What is the best planning step to resolve the conflict before installation?
Cập nhật gần nhất: · quy trình kiểm tra
Đội Ngũ Biên Tập PrepPass · Đối chiếu với California CSLB C-36 Plumbing Trade Examination · Quy trình kiểm tra