Thoát nước, Nước thải & Thông hơiCâu 87 / 360
A vent must rise vertically to a point above the flood-level rim of the highest fixture served before it may offset horizontally, by at least:
a.At the flood-level rim
b.3 inches above
c.6 inches above
d.12 inches above
Giải thích
A vent must rise to at least 6 inches above the flood-level rim of the highest fixture served before offsetting horizontally, so that any drainage backup cannot enter the horizontal vent. Offsetting at or 3 inches above the rim risks fouling the vent, and 12 inches is more than the code minimum.
Trích dẫn luật: 2022 California Plumbing Code (CPC) §905.0Luyện miễn phí toàn bộ 360 câu hỏi — không cần đăng ký.
Câu hỏi liên quan cùng chủ đề
- A circuit vent may serve a battery of not more than how many fixtures?
- A combination waste and vent system is typically used for:
- Horizontal vent piping must be graded so that it:
- What is the minimum diameter permitted for any vent pipe?
- A horizontal branch serves two lavatories (1 DFU each), one kitchen sink (2 DFU), and one bathtub (2 DFU). What is the total DFU and minimum branch size?
- A horizontal drain run is 80 feet long at 1/4 inch per foot slope. What is the total fall over the run?
Cập nhật gần nhất: · quy trình kiểm tra
Đội Ngũ Biên Tập PrepPass · Đối chiếu với California CSLB C-36 Plumbing Trade Examination · Quy trình kiểm tra