Hợp đồng & Thực hiệnCâu 751 / 1605
A contractor prepares a home improvement contract but leaves the completion date blank, intending to 'figure it out later.' This contract:
a.Violates §7159, which requires approximate start and completion dates to be stated
b.Only needs a start date
c.Is fully compliant
d.Is fine because dates are estimates
Giải thích
B&P §7159 requires the contract to state the approximate start and completion dates. Leaving the completion date blank is a violation and reflects a prohibited blank-space practice.
Trích dẫn luật: B&P §7159Luyện miễn phí toàn bộ 1605 câu hỏi — không cần đăng ký.
Câu hỏi liên quan cùng chủ đề
- A landscaping contractor installs an $1,100 sprinkler system at a residence. Which contract rule applies?
- If a home improvement project requires a building permit, the contract should:
- Under a service and repair contract, the total price includes:
- What must a home improvement contract state about extra or unforeseen work discovered mid-project?
- The $500 threshold that triggers a written home improvement contract is measured by:
- A home improvement salesperson may lawfully:
Cập nhật gần nhất: · quy trình kiểm tra
Sen Lin, Người sáng lập PrepPass · Đối chiếu với California CSLB Contractor License Law & Business Exam · Quy trình kiểm tra
Người kiểm duyệt Abraham Chen — Licensed California General Contractor (CSLB License #1101856 — kiểm tra)