What must a home improvement contract state about extra or unforeseen work discovered mid-project?
a.Nothing; surprises are the owner's problem
b.That the contractor may charge any amount without notice
c.That the owner automatically owes double
d.That such work requires a written, signed change order before it is performed and charged
Giải thích
B&P §7159 requires that changes to the contract, including extra work, be documented in a written change order signed by both parties, protecting the owner from unauthorized charges.
Trích dẫn luật: B&P §7159(c)Luyện miễn phí toàn bộ 1605 câu hỏi — không cần đăng ký.
Câu hỏi liên quan cùng chủ đề
- If a home improvement project requires a building permit, the contract should:
- Under a service and repair contract, the total price includes:
- A contractor prepares a home improvement contract but leaves the completion date blank, intending to 'figure it out later.' This contract:
- The $500 threshold that triggers a written home improvement contract is measured by:
- A home improvement salesperson may lawfully:
- Which is TRUE about a home improvement contract that omits the required Mechanics Lien Warning?
Cập nhật gần nhất: · quy trình kiểm tra
Sen Lin, Người sáng lập PrepPass · Đối chiếu với California CSLB Contractor License Law & Business Exam · Quy trình kiểm tra
Người kiểm duyệt Abraham Chen — Licensed California General Contractor (CSLB License #1101856 — kiểm tra)