Which is TRUE about a home improvement contract that omits the required Mechanics Lien Warning?
a.The omission violates §7159 and can subject the contractor to discipline
b.It is unaffected; the warning is optional
c.The warning is only needed for new construction
d.The warning applies only to commercial jobs
Giải thích
The Mechanics Lien Warning is a mandatory element under B&P §7159; omitting it violates the statute and is grounds for disciplinary action.
Trích dẫn luật: B&P §7159Luyện miễn phí toàn bộ 1605 câu hỏi — không cần đăng ký.
Câu hỏi liên quan cùng chủ đề
- What must a home improvement contract state about extra or unforeseen work discovered mid-project?
- The $500 threshold that triggers a written home improvement contract is measured by:
- A home improvement salesperson may lawfully:
- The five-business-day cancellation right is extended to which category of home improvement buyers?
- A homeowner insists on paying the full $30,000 up front to 'lock in the price.' The contractor should know that accepting this:
- Which is a required feature of the progress payment schedule in a home improvement contract?
Cập nhật gần nhất: · quy trình kiểm tra
Sen Lin, Người sáng lập PrepPass · Đối chiếu với California CSLB Contractor License Law & Business Exam · Quy trình kiểm tra
Người kiểm duyệt Abraham Chen — Licensed California General Contractor (CSLB License #1101856 — kiểm tra)