Hợp đồng & Thực hiệnCâu 772 / 1605
Abandoning a home improvement project without legal excuse after starting is:
a.Perfectly acceptable if the contractor is busy
b.A prohibited act and grounds for disciplinary action
c.Only a civil matter with no license consequences
d.Allowed once 10% is complete
Giải thích
B&P §7161 and related statutes make willful abandonment of a construction or home improvement project without legal excuse a prohibited act and cause for CSLB discipline.
Trích dẫn luật: B&P §7161Luyện miễn phí toàn bộ 1605 câu hỏi — không cần đăng ký.
Câu hỏi liên quan cùng chủ đề
- A contractor uses one contract to cover both a $400 gutter cleaning and a $9,000 addition, calling the whole thing a 'service call.' The addition portion:
- When a contract funds are placed in an approved joint control, the joint control company's role is to:
- A home improvement contract must be dated. The date is important primarily because it:
- A contractor's home improvement contract lists the total price but no breakdown of the payment schedule. Under §7159, this is:
- A homeowner requests a $500 furnace repair by phone. The contractor may present a service and repair contract that must include:
- A contractor prints two identical cancellation notices and attaches them to the contract. This satisfies the requirement that the buyer receive:
Cập nhật gần nhất: · quy trình kiểm tra
Sen Lin, Người sáng lập PrepPass · Đối chiếu với California CSLB Contractor License Law & Business Exam · Quy trình kiểm tra
Người kiểm duyệt Abraham Chen — Licensed California General Contractor (CSLB License #1101856 — kiểm tra)