Hợp đồng & Thực hiệnCâu 774 / 1605
A homeowner requests a $500 furnace repair by phone. The contractor may present a service and repair contract that must include:
a.Required notices including a description of the work and consumer-protection language
b.A 10-year exclusive service clause
c.A demand for full prepayment
d.The homeowner's financial statements
Giải thích
Even the streamlined service and repair contract under §7159.10 must include specified content, such as a description of the requested work and the mandated consumer notices.
Trích dẫn luật: B&P §7159.10Luyện miễn phí toàn bộ 1605 câu hỏi — không cần đăng ký.
Câu hỏi liên quan cùng chủ đề
- A home improvement contract must be dated. The date is important primarily because it:
- Abandoning a home improvement project without legal excuse after starting is:
- A contractor's home improvement contract lists the total price but no breakdown of the payment schedule. Under §7159, this is:
- A contractor prints two identical cancellation notices and attaches them to the contract. This satisfies the requirement that the buyer receive:
- On a $3,000 fence job with no joint control, the maximum lawful down payment is:
- The requirement that a home improvement contract be signed before work begins protects the buyer by:
Cập nhật gần nhất: · quy trình kiểm tra
Sen Lin, Người sáng lập PrepPass · Đối chiếu với California CSLB Contractor License Law & Business Exam · Quy trình kiểm tra
Người kiểm duyệt Abraham Chen — Licensed California General Contractor (CSLB License #1101856 — kiểm tra)