Hợp đồng & Thực hiệnCâu 812 / 1605
A written change order in construction is best described as:
a.A notice that the contractor is quitting the job
b.A separate lawsuit filed against the owner
c.A verbal understanding that scope has changed
d.A written amendment documenting an agreed change in scope, price, and/or schedule
Giải thích
A change order is a written amendment to the original contract that documents an agreed-upon change in the scope of work, the contract price, the schedule, or all three. Reducing changes to writing protects both parties by creating a clear record and preventing disputes over extras. A verbal understanding is risky and often disputed; a change order is the formal, signed instrument that alters the existing agreement, not a lawsuit or a termination notice.
Luyện miễn phí toàn bộ 1605 câu hỏi — không cần đăng ký.
Câu hỏi liên quan cùng chủ đề
- The doctrine of 'substantial performance' generally allows a contractor who has performed in good faith with only minor, non-material defects to:
- Specific performance, a remedy that compels a party to actually perform the contract, is most commonly granted in disputes involving:
- Rescission as a contract remedy means:
- During a remodel, the owner asks the contractor to add a skylight not in the original plans. The BEST practice before performing this extra work is to:
- A contractor performs extra work at the owner's oral request but has no written change order. When the owner refuses to pay, the contractor's recovery may still be possible under which theory?
- Which statement about oral change orders on a construction project is most accurate?
Cập nhật gần nhất: · quy trình kiểm tra
Sen Lin, Người sáng lập PrepPass · Đối chiếu với California CSLB Contractor License Law & Business Exam · Quy trình kiểm tra
Người kiểm duyệt Abraham Chen — Licensed California General Contractor (CSLB License #1101856 — kiểm tra)