Which statement about oral change orders on a construction project is most accurate?

a.They are always fully enforceable and preferred
b.They are risky because scope and price disputes are hard to prove, and written change orders are strongly preferred
c.They automatically void the entire original contract
d.They convert the contract into a public works contract

Giải thích

Oral change orders are legally possible in some situations but are risky because they invite later disputes over exactly what was agreed and at what price, which are difficult to prove. Written change orders are strongly preferred and, for many contracts, required. An oral change does not transform a private job into public works, nor does it void the original contract; it simply creates evidentiary and, sometimes, compliance problems.

Luyện miễn phí toàn bộ 1605 câu hỏi — không cần đăng ký.

Câu hỏi liên quan cùng chủ đề

Cập nhật gần nhất: · quy trình kiểm tra

Sen Lin, Người sáng lập PrepPass · Đối chiếu với California CSLB Contractor License Law & Business Exam · Quy trình kiểm tra
Người kiểm duyệt Abraham Chen Licensed California General Contractor (CSLB License #1101856 kiểm tra)
Báo lỗi