Hợp đồng & Thực hiệnCâu 822 / 1605
A unit-price contract is most appropriate when:
a.The owner wants a single fixed total with no measurement
b.The parties want to bill only by the hour
c.The entire scope and quantities are precisely known in advance
d.The exact quantities are uncertain, so the parties agree on a price per unit (for example, per cubic yard of excavation)
Giải thích
A unit-price contract sets a price per unit of work, such as per cubic yard of excavation or per linear foot of pipe, and the final total is the unit price multiplied by the actual measured quantities. It suits projects where quantities cannot be pinned down in advance, like earthwork. When quantities are precisely known, a lump sum fits better; unit pricing specifically handles quantity uncertainty by measuring actual work performed.
Luyện miễn phí toàn bộ 1605 câu hỏi — không cần đăng ký.
Câu hỏi liên quan cùng chủ đề
- In a fixed-price (lump-sum) contract, the contractor generally:
- Under a cost-plus contract, the contractor is typically paid:
- A 'cost-plus with a guaranteed maximum price (GMP)' contract protects the owner by:
- In a time-and-materials (T&M) contract, the contractor is compensated based on:
- Which contract type places the greatest risk of cost overruns on the contractor rather than the owner?
- A liquidated damages clause in a construction contract is best described as:
Cập nhật gần nhất: · quy trình kiểm tra
Sen Lin, Người sáng lập PrepPass · Đối chiếu với California CSLB Contractor License Law & Business Exam · Quy trình kiểm tra
Người kiểm duyệt Abraham Chen — Licensed California General Contractor (CSLB License #1101856 — kiểm tra)