In a time-and-materials (T&M) contract, the contractor is compensated based on:

a.A price per completed unit only
b.A guaranteed maximum with no cost tracking
c.One fixed lump-sum price agreed at the outset
d.The actual labor hours worked at agreed rates plus the cost of materials (often with markup)

Giải thích

A time-and-materials contract pays the contractor for actual labor hours at agreed hourly rates plus the cost of materials used, frequently with an agreed markup on materials for overhead and profit. It is well suited to work of uncertain scope, such as repairs or troubleshooting. It differs from a fixed lump sum, from unit pricing (per unit of quantity), and requires accurate records of hours and material costs to support invoices.

Luyện miễn phí toàn bộ 1605 câu hỏi — không cần đăng ký.

Câu hỏi liên quan cùng chủ đề

Cập nhật gần nhất: · quy trình kiểm tra

Sen Lin, Người sáng lập PrepPass · Đối chiếu với California CSLB Contractor License Law & Business Exam · Quy trình kiểm tra
Người kiểm duyệt Abraham Chen Licensed California General Contractor (CSLB License #1101856 kiểm tra)
Báo lỗi