For a liquidated damages clause to be enforceable rather than struck down as a penalty, courts generally require that:
a.The clause be notarized
b.The stated amount be a reasonable estimate of anticipated damages that would otherwise be difficult to determine
c.Actual damages be easy to calculate
d.The amount be at least triple the actual loss
Giải thích
A liquidated damages provision is enforceable when, at the time of contracting, the fixed amount is a reasonable estimate of the harm that a breach would cause and actual damages would be difficult or impractical to determine. If the amount is grossly disproportionate to any anticipated loss, courts treat it as an unenforceable penalty. Notarization is irrelevant, and the doctrine applies precisely because actual damages are hard, not easy, to calculate.
Trích dẫn luật: California Civil Code §1671Luyện miễn phí toàn bộ 1605 câu hỏi — không cần đăng ký.
Câu hỏi liên quan cùng chủ đề
- In a time-and-materials (T&M) contract, the contractor is compensated based on:
- Which contract type places the greatest risk of cost overruns on the contractor rather than the owner?
- A liquidated damages clause in a construction contract is best described as:
- A contract states, 'Liquidated damages of $500 per day shall apply for each day completion is late beyond the substantial completion date.' If the contractor finishes 10 days late, the owner's presumptive recovery under a valid clause is:
- When a contract states that 'time is of the essence,' it means:
- In the absence of a 'time is of the essence' clause or a specified completion date, a contractor is generally obligated to complete the work:
Cập nhật gần nhất: · quy trình kiểm tra
Sen Lin, Người sáng lập PrepPass · Đối chiếu với California CSLB Contractor License Law & Business Exam · Quy trình kiểm tra
Người kiểm duyệt Abraham Chen — Licensed California General Contractor (CSLB License #1101856 — kiểm tra)