Tài chính doanh nghiệpCâu 1126 / 1605
A contractor pays a mason $28/hour. With payroll burden (taxes, insurance, benefits) adding 35%, what is the fully burdened labor rate?
a.$28.00
b.$36.40
c.$37.80
d.$42.00
Giải thích
Burden adds 35% to the base wage: $28 x 1.35 = $37.80 per hour. Estimators must use the fully burdened rate, not the base wage, or labor will be underestimated.
Luyện miễn phí toàn bộ 1605 câu hỏi — không cần đăng ký.
Câu hỏi liên quan cùng chủ đề
- A contractor estimates a job at 120 labor hours. Actual hours worked were 150. By what percentage did labor hours exceed the estimate?
- The primary purpose of JOB COSTING is to:
- A concrete slab is 30 ft x 40 ft x 4 inches thick. How many cubic yards of concrete are needed? (1 cubic yard = 27 cubic feet)
- A painting job covers 2,400 square feet. One gallon covers 350 sq ft. How many gallons (rounded up to full cans) are needed for two coats?
- A subcontractor bids $18,000. The general contractor adds a 12% markup on that subcontract. What is the marked-up amount billed to the owner for that scope?
- A good estimate should include a contingency allowance primarily to:
Cập nhật gần nhất: · quy trình kiểm tra
Sen Lin, Người sáng lập PrepPass · Đối chiếu với California CSLB Contractor License Law & Business Exam · Quy trình kiểm tra
Người kiểm duyệt Abraham Chen — Licensed California General Contractor (CSLB License #1101856 — kiểm tra)