A good estimate should include a contingency allowance primarily to:

a.Raise the contractor's profit margin
b.Fund the five percent retention the owner withholds
c.Absorb unforeseen conditions and bid error
d.Cover the change orders the owner later requests

Giải thích

A contingency is money set aside inside the estimate to absorb unforeseen site conditions and the normal imprecision of estimating, so a small surprise does not have to become a claim. It is not profit: spending it leaves the margin intact, while treating it as profit means pricing the risk twice. Retention is the owner's money withheld from payments - five percent on public works under Public Contract Code section 7201, and capped at five percent on private contracts entered into on or after 1 January 2026 by Civil Code section 8811 - so it is money not yet received rather than a cost to fund. And owner-requested changes are paid through change orders at agreed prices, which is why they sit outside the contingency.

Trích dẫn luật: Public Contract Code §7201; Civil Code §8811

Luyện miễn phí toàn bộ 1632 câu hỏi — không cần đăng ký.

Own the complete CSLB Law & Business guide — PDF + EPUB, $24.99 →

Câu hỏi liên quan cùng chủ đề

Cập nhật gần nhất: · quy trình kiểm tra

Đội ngũ PrepPass · Đối chiếu với California CSLB Contractor License Law & Business Exam · Quy trình kiểm tra
Người kiểm duyệt Abraham Chen — Licensed California General Contractor (CSLB License #1101856 — kiểm tra)
Báo lỗi