A good estimate should include a contingency allowance primarily to:
Giải thích
A contingency is money set aside inside the estimate to absorb unforeseen site conditions and the normal imprecision of estimating, so a small surprise does not have to become a claim. It is not profit: spending it leaves the margin intact, while treating it as profit means pricing the risk twice. Retention is the owner's money withheld from payments - five percent on public works under Public Contract Code section 7201, and capped at five percent on private contracts entered into on or after 1 January 2026 by Civil Code section 8811 - so it is money not yet received rather than a cost to fund. And owner-requested changes are paid through change orders at agreed prices, which is why they sit outside the contingency.
Trích dẫn luật: Public Contract Code §7201; Civil Code §8811Luyện miễn phí toàn bộ 1632 câu hỏi — không cần đăng ký.
Own the complete CSLB Law & Business guide — PDF + EPUB, $24.99 →
Câu hỏi liên quan cùng chủ đề
- A contractor pays a mason $28/hour. With payroll burden (taxes, insurance, benefits) adding 35%, what is the fully burdened labor rate?
- A painting job covers 2,400 square feet. One gallon covers 350 sq ft. How many gallons (rounded up to full cans) are needed for two coats?
- A subcontractor bids $18,000. The general contractor adds a 12% markup on that subcontract. What is the marked-up amount billed to the owner for that scope?
- Working capital is calculated as:
- A contractor has current assets of $150,000 and current liabilities of $90,000. What is his working capital?
- Poor cash flow on a construction project is MOST often caused by:
Cập nhật gần nhất: · quy trình kiểm tra