Poor cash flow on a construction project is MOST often caused by:

a.Paying suppliers early to take their discount
b.Holding retention back from all the subcontractors
c.Billing the owner monthly rather than weekly
d.Paying labour and materials before billings land

Giải thích

The structural cause is timing: wages and material invoices fall due weeks before the owner pays a progress billing, and retention delays part of the receipt further still, so cash drains even on a profitable job. Taking an early-payment discount does consume cash, but it buys a return and is a choice rather than the cause. Monthly billing lengthens the gap and makes the problem worse, without being its origin. Withholding retention from subs conserves the contractor's cash rather than draining it.

Luyện miễn phí toàn bộ 1632 câu hỏi — không cần đăng ký.

Own the complete CSLB Law & Business guide — PDF + EPUB, $24.99 →

Câu hỏi liên quan cùng chủ đề

Cập nhật gần nhất: · quy trình kiểm tra

Đội ngũ PrepPass · Đối chiếu với California CSLB Contractor License Law & Business Exam · Quy trình kiểm tra
Người kiểm duyệt Abraham Chen — Licensed California General Contractor (CSLB License #1101856 — kiểm tra)
Báo lỗi