A cash flow projection primarily helps a contractor:
a.Foresee cash shortfalls in time to arrange credit
b.Set the overhead rate each bid should carry
c.Value the work in progress for the balance sheet
d.Compute the depreciation on owned equipment
Giải thích
A cash flow projection lays expected receipts against expected disbursements week by week, so a shortfall is visible before it arrives and a line of credit or a change in billing can be arranged in time. Markup comes from the overhead rate and the target margin, not from a cash schedule. Work in progress is valued from job-cost records against the contract amounts. Depreciation follows the asset's cost and schedule and is a tax and book calculation, with no cash timing in it at all.
Luyện miễn phí toàn bộ 1632 câu hỏi — không cần đăng ký.
Own the complete CSLB Law & Business guide — PDF + EPUB, $24.99 →
Câu hỏi liên quan cùng chủ đề
- Poor cash flow on a construction project is MOST often caused by:
- Why can a contractor be profitable on paper yet still run out of cash?
- A contractor offers 2/10, net 30 terms and pays a $10,000 supplier invoice on day 8. How much does he pay?
- The current ratio is calculated as:
- A contractor has current assets of $200,000 and current liabilities of $80,000. What is his current ratio?
- Which financial statement reports a company's assets, liabilities, and owner's equity at a single point in time?
Cập nhật gần nhất: · quy trình kiểm tra
Đội ngũ PrepPass · Đối chiếu với California CSLB Contractor License Law & Business Exam · Quy trình kiểm tra
Người kiểm duyệt Abraham Chen — Licensed California General Contractor (CSLB License #1101856 — kiểm tra)