AdministrationCâu 88 / 110
A change order adds two lavatories at 1 DFU each and one water closet at 4 DFU to a branch. By how many drainage fixture units does the branch load increase, so plan review can confirm the pipe is still adequate?
a.4 DFU
b.8 DFU
c.10 DFU
d.6 DFU
Giải thích
Added load = (2 x 1) + (1 x 4) = 2 + 4 = 6 DFU. A change order that adds fixtures raises the drainage fixture-unit load, so a plan revision must confirm the existing branch and stack still have capacity before the work is installed. If the new total exceeds the pipe capacity, the branch must be enlarged.
Trích dẫn luật: UPC §703.0Luyện miễn phí toàn bộ 110 câu hỏi — không cần đăng ký.
Câu hỏi liên quan cùng chủ đề
- During plan review, minimum fixtures are checked against occupancy: the table requires one water closet per 50 occupants. The occupant load is 175. What is the minimum number of water closets required?
- A finished DWV system is given a final air test instead of water. The system is pressurized to 5 psi and must hold for 15 minutes. What is the pass criterion?
- A base permit fee is $290. The jurisdiction adds a 12 percent state surcharge on the permit fee plus a flat $40 plan-review fee. What is the total the contractor pays?
- An inspector finds that a backflow assembly was installed but never tested by a certified tester. What documentation closes this item?
- A master plumber must schedule labor. A job is estimated at 240 labor-hours and the crew provides 3 plumbers working 8-hour days. How many working days are needed?
- The adopted plumbing code and a manufacturer's installation instructions differ on the maximum length of a listed flexible water connector. Which controls, and what is the guiding principle?
Cập nhật gần nhất: · quy trình kiểm tra
Đội Ngũ Biên Tập PrepPass · Đối chiếu với Master Plumber Licensing Exam (UPC/IPC-based) · Quy trình kiểm tra