PrepPass 团队 · 依据官方资料核对 CSLB Solar (C-46) study guide 13E-46 (03-2026), California statutes, Cal/OSHA Title 8 and DOE/NREL publications, read September 2026 · 我们如何核对
免费试读 · 在线阅读第 3 章

PV System Installation, Part 1: Basic PV Systems and Labeling (CSLB Section 3)

这是《CSLB C-46 Solar Trade Exam Study Guide (2026)》的第 3 章 —— 完整的一章,直接在此免费阅读;无需下载,无需邮箱。内容与电子书正文完全一致。读到结尾,完整指南只差一次点击。

我们没有拿轻松的绪论充数 —— 这一免费章节直接翻到书里最见功力的部分,让你在考试真正难的地方检验这本书讲得好不好。

Photovoltaic (PV) System Installation and Commissioning is the largest section of the C-46 examination at 28 percent[1] — more than a quarter of your score. The CSLB lists six topics: install basic PV systems, install energy storage systems (ESS), interface with the utility grid, install standalone PV systems, label PV components, and system testing, configuration and monitoring, including educating the client[1]. This chapter covers the first and the fifth: building a grid-tied PV system from the array to the point of interconnection, and labeling it. Chapter 4 covers storage, the utility interface, stand-alone systems and commissioning.

The code references here are to the California Electrical Code (CEC), which the C-46 study guide lists in its 2022 edition[1]. Where the 2025 edition that took effect on January 1, 2026[2] is reflected in a county checklist, we say so.

3.1 Install basic PV systems

The power path

A grid-tied PV system is a chain. Know the links in order, because the examination asks where things go:

  1. PV modules, wired in series into strings (source circuits).
  2. Module-level electronics where used: microinverters, DC-DC converters, or rapid shutdown devices.
  3. DC wiring from the array, through the roof, to the inverter — in metal where it runs inside the building[3].
  4. The inverter, which "converts direct current (DC) electricity, which is what a solar panel generates, to alternating current (AC) electricity, which the electrical grid uses"[4].
  5. AC disconnecting means and overcurrent protection.
  6. The point of interconnection with the building's electrical service.
  7. Grounding and bonding throughout.

Listed equipment, installed as listed

Everything in that chain must be listed for its use. San Diego County's 2025-code checklist: "All proposed equipment shall be listed or field labeled for PV application by a nationally recognized testing agency"[5]. The Guidebook's inspection list starts with the inverter: "Inverters are listed to UL 1741," and "grid-tied system inverters need to be identified for use in interactive power systems"[6]. State law says the same thing at the top level — an electric solar system must meet the California Electrical Code and the standards of accredited testing laboratories such as Underwriters Laboratories[7].

Installing as listed also protects what is already there. Berkeley's checklist requires the installer to "ensure that any alterations or additions to the existing system(s) shall not cause existing equipment or components to lose their listings"[3], and requires the equipment, wiring and interconnections to be "installed by a qualified person trained per NFPA 70E 2018"[3].

Conductors and connections

  • Outdoors: "All exposed wiring shall be listed for wet location and sunlight resistant"[5].
  • Inside the building: DC PV circuits in metal raceway, MC cable, or metal enclosures[3].
  • Sizing: the two 1.25 factors on the DC side (Chapter 1)[8]; San Diego County also requires wire sizing and terminations "in conformance with the seventy-five-degree (75°) column" of the ampacity tables[5], because terminals are usually rated 75 °C.
  • Heat: rooftop conductors can reach 65–75 °C near modules on still, hot days[8], which is why temperature correction matters.
  • Terminations: "Crimp terminals are listed and installed using a listed tool specified for use in crimping those specific crimps," and "pressure terminals are listed for the environment and tightened to manufacturer recommended torque specifications"[6].
  • Connectors: where a PV connector includes an equipment-grounding member, it "shall make first and break last"[8].
  • DC overcurrent devices: "DC breakers shall be listed and rated for PV use"[5].

Named trap — AC ratings on DC equipment. A breaker or switch rated only for AC may not interrupt a DC arc. DC PV circuits need devices listed and rated for DC PV use.

Arc-fault protection

PV systems at higher DC voltages must detect and interrupt arcing faults. Berkeley's 2022-code checklist: "PV systems operating at a maximum system voltage of 80 volts or greater, shall be protected as specified in CEC 690.11"[3]. Most string inverters include DC arc-fault circuit protection; the Guidebook's standard plan asks directly whether the inverter has "Integrated DC Arc-Fault Circuit Protection?"[6].

Grounding and bonding

Grounding gives fault current a path and keeps metal parts at earth potential; bonding ties the metal parts together.

  • System grounding configuration follows CEC 690.41, and the grounding electrode system follows 690.47, as San Diego County's checklist states[5].
  • Interconnected sources "shall be grounded in accordance with CEC 250"[3].
  • Module frames and racking are bonded per the module listing — through listed grounding devices named in the module instructions, or UL 2703-listed devices whose instructions name the module[5].
  • Electrodes: a second ground rod at least 6 feet from the first[5]; a supplemental electrode where a metal water pipe is the only electrode[5]; and the service electrode "must be verified at the time of inspection"[5].

Disconnecting means

A PV system must be separable from everything it connects to. Berkeley's checklist: disconnecting means "shall be provided to disconnect the PV system from all wiring systems including power systems, energy storage systems, and utilization equipment and its associated premises wiring," and "the PV system disconnecting means shall be installed at a readily accessible location"[3]. For individual pieces of equipment such as an inverter, "isolating devices or equipment disconnecting means shall be installed in circuits connected to equipment at a location within the equipment, or within sight and within 10 feet of the equipment"[3].

The 2022 CEC's rules for a power source's disconnecting means (section 705.20) include that it must:

  • "Simultaneously disconnect all ungrounded conductors of the circuit"[9];
  • "Plainly indicate whether in the open (off) or closed (on) position"[9];
  • carry a warning where the line and load terminals can both be energized when open[9].

That warning matters because "with interconnected power sources, some equipment, including switches and fuses, is likely to be energized from both directions"[9], and San Diego County reminds inspectors that "all terminals of the disconnecting means may be energized in the open position"[5]. Opening a PV disconnect does not make the array side dead: open-circuit voltage "would still be present on the array wiring and in the disconnect box"[8].

The Guidebook's inspection list adds that "listed AC and DC disconnects and overcurrent protection are grouped and identified"[6]. San Diego County requires microinverter and integrated systems to have a rooftop AC disconnect[5].

Rapid shutdown

Rapid shutdown exists for firefighters. When it is initiated, the PV conductors on and in the building must drop to low voltage quickly. Berkeley's summary of CEC 690.12 (2022 edition):

ConductorsLimit after initiation
Outside the array boundary, or more than 3 feet from the point of entry inside a buildingNot more than 30 volts within 30 seconds[3]
Inside the array boundaryNot more than 80 volts within 30 seconds[3]

"Voltage and power shall be measured between any two conductors and between any conductor and ground"[3]. The requirements apply only to PV circuits supplied by the PV system[3].

The initiation device "shall be located at a readily accessible location outside the building"[3] and may be the service disconnecting means, the PV system disconnecting means, or a readily accessible switch that plainly shows whether it is "off" or "on"[3]. The Guidebook adds that the device's location "shall be shown on the site plan drawing"[6]. Equipment that performs the rapid shutdown function (other than the initiation device itself) "shall be listed for providing rapid shutdown protection"[3]; Poway's list requires the rapid shutdown system to be UL 1741 listed[10].

Named trap — rapid shutdown is not zero volts. Rapid shutdown reduces voltage to the limits above within 30 seconds. It does not de-energize the array. A DOE-hosted fire service presentation warns that "when RSS is initiated, firefighters may think system is de-energized to zero"[11] — the same misunderstanding the examination likes to test.

The point of interconnection

A grid-tied inverter's AC output joins the building's electrical system in one of two places.

Load-side connection. "The output of a utility-interactive inverter shall be permitted to be connected to the load side of the service disconnecting means of the other source(s) at any distribution equipment on the premises"[3]. The Guidebook's inspection list wants the connection "at a dedicated breaker or disconnect"[6], and "where a back-fed breaker is used as a utility interconnection means, the breaker is not marked 'line and load'"[6].

The busbar must not be overloaded by two sources feeding it. The rules, as the Guidebook and Berkeley state them:

  • Use 125 percent of the inverter output circuit current in ampacity calculations for feeders, taps and busbars[3].
  • If the PV breaker is at the opposite end of the busbar from the main breaker or feeder, "the sum of 125% of the inverter output circuit currents and the rating of the overcurrent device protecting the busbar shall not exceed 120% of the ampacity of the busbar"[6]. San Diego County requires the PV connection "at the opposite (load) end from the input feeder location or main circuit location"[5].
  • If the PV breaker is not at the opposite end, the Guidebook's standard plan falls back to the 100 percent row of its table[6].

Worked example 3-1 (the 120 percent rule). A 200-amp busbar is protected by a 200-amp main breaker. The PV breaker will be at the opposite end. 120% of 200 A = 240 A. 240 − 200 = 40 A of PV breaker allowed. An inverter with a continuous output of 32 A needs 32 × 1.25 = 40 A — it just fits. An inverter of 35 A needs 43.75 A — it does not.

Worked example 3-2 (a bigger busbar). The panel has a 225-amp busbar and a 200-amp main. 120% × 225 = 270 A. 270 − 200 = 70 A allowed. The Guidebook's own table caps its standard plan at 60 A for a 225 A busbar with a 200 A main because the plan is limited to 10 kW[6].

Worked example 3-3 (de-rating the main). A 200 A busbar with a 200 A main cannot take a 50 A PV breaker. Replacing the main with a 175 A breaker gives 240 − 175 = 65 A allowed. Where approved plans de-rate the main breaker, San Diego County requires a placard at the panel reading "THIS PANEL HAS BEEN DE-RATED TO (insert amperage size). DO NOT INSTALL LARGER BREAKERS."[5] — and the building's loads must still be served by the smaller main.

Supply-side connection. An electric power production source may instead be "connected to the supply side of the service disconnecting means"[3]. Then "the sum of the ratings of all overcurrent devices connected to power production sources shall not exceed the rating of the service"[3]. In equipment under the utility's exclusive control, such as a meter socket, "only connections approved by the electric utility shall be permitted"[9].

Power control systems. The 2022 CEC allows a listed power control system (PCS) to limit current: "the setting of the PCS controller shall be considered the power-source output circuit current" in the load-side calculations[9]. San Diego County's 2025-code checklist describes a PCS that can "increase or decrease PV/ESS outputs based on the home's real-time demand, ensuring the outputs never exceed the main panel's busbar rating"[5].

Two more interconnection rules.

  • "No multiwire branch circuits are installed where single 120-volt inverters are connected to 120/240- volt load centers"[6] — a shared neutral could be overloaded.
  • Surge protection. In the 2022 CEC, "all services supplying dwelling units shall be provided with a surge-protective device (SPD)"[10], a Type 1 or Type 2 device[10], integral to or immediately adjacent to the service equipment[10]; "where service equipment is replaced, all of the requirements of this section shall apply"[10]. A PV job that replaces the main panel picks up this requirement.

Working space

Inverters, disconnects and panelboards need working space for operation and maintenance. The Guidebook's inspection list: "Access and working space for operation and maintenance of PV equipment such as inverters, disconnecting means and panelboards (not required for PV modules)"[6].

Sources cited in this excerpt

  1. Contractors State License Board License Examination Study Guide: Solar (C-46), form 13E-46 (03-2026), for examinations scheduled on or after July 1, 2023. Contractors State License Board (CSLB), 2026-03. https://www.cslb.ca.gov/Resources/StudyGuides/C46StudyGuide.pdf
  2. California Building Standards Code (Title 24) editions, Building Standards Commission web page retrieved 2026-09-24. California Building Standards Commission, 2026-09-24. https://www.dgs.ca.gov/BSC/Codes
  3. Code Compliance Checklist, Solar Photovoltaic (Form 166), citing the 2022 California codes, last revised 02/23/23. City of Berkeley, Building and Safety Division, 2023-02-23. https://berkeleyca.gov/sites/default/files/documents/166%20CCC%20-%20Solar%20Photovoltaic_1.pdf
  4. Solar Integration: Inverters and Grid Services Basics, U.S. Department of Energy web page retrieved 2026-09-24. 2026-09-24. https://www.energy.gov/cmei/systems/solar-integration-inverters-and-grid-services-basics
  5. Photovoltaic and energy storage checklist PDS 081S, citing the 2025 California codes, rev. 02/19/2026. County of San Diego, Planning & Development Services, 2026-02-19. https://www.sandiegocounty.gov/content/dam/sdc/pds/docs/pds081s.pdf
  6. California Solar Permitting Guidebook, 4th Edition (standard plans, checklists and inspection guides; written to the 2016 California codes). Governor's Office of Planning and Research, State of California, 2019-02. https://lci.ca.gov/wp-content/uploads/20190226-Solar_Permitting_Guidebook_4th_Edition.pdf
  7. California Government Code section 65850.5 (solar energy system permitting), leginfo text retrieved 2026-09-24. California Legislative Information, 2026-09-24. https://leginfo.legislature.ca.gov/faces/codes_displaySection.xhtml?lawCode=GOV&sectionNum=65850.5
  8. Photovoltaic Power Systems and the National Electrical Code: Suggested Practices (SAND2001-0674), written to the 1999 NEC. Sandia National Laboratories, U.S. Department of Energy, 2001-03. https://www.osti.gov/servlets/purl/808812
  9. Changes for Solar in the California 2022 Codes (excerpts of the 2022 CRC, CEC, CFC and Energy Code as adopted). County of Lake, Community Development Department, Building Division, 2022-11-30. https://www.lakecountyca.gov/DocumentCenter/View/5644/Changes-for-Residential-Solar-California-2022-Codes
  10. City of Poway Solar Compliance List, citing the 2022 California codes, revised 03/2024. City of Poway, Development Services Department, Building Division, 2024-03. https://poway.org/DocumentCenter/View/11079/Poway-Solar-Compliance-List-PDF
  11. PV and Firefighter Operations (Manchester Fire Department presentation hosted by the U.S. Department of Energy). U.S. Department of Energy (host), 2016-10. https://www.energy.gov/sites/default/files/2016/10/f33/PV%20and%20Firefighter%20Operations%20-%20Manchester%20Fire.pdf
你已读完免费章节

获取完整指南

刚才是全书 7 章中的第 3 章 —— 完整的一章,与正式版一字不差。其余各章以同样的深度讲透考试的每个部分,还附带练习题与答案解析 —— 一份可永久保存的干净 PDF 与 EPUB。

同一门考试,零头的价格
$200–$800→$24.99

CSLB exam prep course 要 $200–$800。这本书讲的是同一门考试 —— 深度就是你刚读到的这样 —— 只需一次性 $24.99,永久归你。

  • 7 chapters covering all six CSLB sections, weighted 14/17/28/7/15/19
  • 7 chapter quizzes plus a 100-question practice exam
  • Worked calculations: cold string voltage, PV current factors, the 120% busbar rule, battery kWh, pool volume and Btu
  • A table of where the 2022 and 2025 California codes place each rule
  • Six job walk-throughs plus formula and key-number appendices
  • 209 original questions, each with a worked explanation citing its source
  • PDF + EPUB you keep

拥有整本书 — PDF + EPUB

练习题和计时模考永远免费。这本书是「学」的那一半:

  • 逐章系统讲解——每个考试章节按顺序讲透,不只是刷题
  • 可打印、贴标签——一本能划重点、做标记的纸质参考书
  • 离线可用——PDF 用来打印,EPUB 放进手机或阅读器
  • 全部在一个文件里——所有章节集中一处,可搜索、可打印

本书为英文版,下载的 PDF 与 EPUB 均为英文。

$24.99一次买断 · 永久下载 · 无订阅

14 天退款保证——不满意?发邮件即可全额退款,无需理由。 退款政策

本站提供免费样章——先读后买。一次付款解锁整本书,PDF + EPUB 永久保存。

不止考一门?有套装价

  • CSLB Law & Business — Complete Study Guide (2026)$24.99
  • CSLB C-46 Solar Trade Exam Study Guide (2026)$24.99
  • CSLB Law & Business — Cram Sheet (2026)$9.99

3 件一起买:$30.99 —— 比分开买省 $28.98

分开买 $59.97 · 立减 48% · 一次结账,共 3 件。

已经买过《CSLB Law & Business》了?那就别买套装——套装里含这本,你会重复付费。单独购买《CSLB C-46 Solar》只要 $24.99。 CSLB C-46 Solar · 套装内容 →

一次买断 $24.99 · PDF + EPUB · 永久归你 · 查看完整目录。

免费试读 —— CSLB C-46 Solar 学习指南中完整的一章。仅为教育性摘要,非专业或法律意见 —— 请始终以官方来源核实当前规定。最后更新:August 2026。

反馈