企业组织与执照第 1455 / 1632 题
A contractor performs work outside the classifications listed on the license. This is best characterized as what?
a.Permitted, because holding any active license satisfies the license law
b.Permitted where the out-of-scope portion is incidental to the contract
c.Acting outside the license scope, a violation subject to discipline
d.Permitted if the out-of-scope portion is under $1,000 in value
解析
B&P §7059 confines a licensee to the classifications held; exceeding them is a violation, and under §7031 the contractor may be barred from collecting for work it was not licensed to perform. (a) treats a license as a general permit rather than a scope. (b) is the genuinely hard distractor: work that is truly incidental and supplemental to the licensed trade is allowed, so the item turns on whether the work is incidental — if it is a separate trade, it is not. (d) borrows the §7048 minor-work exemption, which excuses the absence of a license on a small standalone job and does nothing about scope.
法律依据: B&P Code §7059 / §7031免费刷完整 1632 道题库 — 无需注册。
Own the complete CSLB Law & Business guide — PDF + EPUB, $24.99 →
同考点相关题目
- A claimant recovers against the contractor's license bond and the surety pays. What may the surety then do?
- A home improvement salesperson registration is tied to what?
- Why does California require home improvement salespersons to register with the CSLB?
- A key difference between the $25,000 contractor's license bond and the disciplinary bond is that the disciplinary bond is required when?
- How long must a disciplinary bond generally be maintained after it is required?
- An RME may qualify only one active license at a time unless what condition is met regarding ownership?
最近核对: · 审核流程
PrepPass 团队 · 依据官方资料核对 California CSLB Contractor License Law & Business Exam · 我们如何核对