企业组织与执照第 1359 / 1605 题
On a single-trade project involving only framing, may a Class B General Building contractor take the prime contract and self-perform that single trade?
a.Yes, in all cases without limitation
b.No, a Class B may never contract for a single trade
c.Only if the contract requires at least two unrelated trades, or the contractor holds the appropriate specialty classification
d.Only with written CSLB pre-approval for each job
解析
Under B&P Code section 7057, a General Building contractor may contract to perform a project only when it involves at least two unrelated trades, unless the contractor holds the specialty classification for the single trade or subcontracts that trade to a properly licensed specialist.
法律依据: B&P Code §7057免费刷完整 1605 道题库 — 无需注册。
同考点相关题目
- A contractor wants to build residential and commercial buildings that require the use of at least two unrelated building trades or crafts. Which license classification is appropriate?
- A firm specializes in building highways, dams, and other fixed works requiring specialized engineering knowledge. Which classification must it hold?
- A contractor installs only electrical wiring and equipment on a project and performs no other trade. Which classification fits this work?
- Which of the following best describes the 'two unrelated trades' rule for a Class B General Building contractor?
- What is the required amount of the contractor's license bond for an active California contractor's license?
- When the CSLB requires a bond of qualifying individual because an RMO or RME owns less than 10% of the entity, what is the required amount?