A contractor breaks a $3,000 job into four separate $750 invoices to stay under the license threshold. Is that permitted?

a.Yes, since each of the separate invoices is under $1,000
b.Yes, if the customer agrees to be invoiced in stages
c.No, because the aggregate price of the operation controls
d.No, unless no phase of the work needs a building permit

解析

B&P §7048(a) measures the exemption by the aggregate contract price for labor, materials, and all other items on one undertaking or project, and §7048(b) removes the exemption where the work is part of a larger operation or where the operation is divided into contracts of less than $1,000 to evade the chapter. The job is a $3,000 project and needs a license. (a) reads the paperwork rather than the project. (b) makes the customer's agreement decisive, which no exemption does. (d) states a real condition of §7048(a) — the work must require no building permit — but applies it to phases instead of to the whole project, and no permit test rescues a job split for evasion.

法律依据: B&P Code §7048(a)-(b)

免费刷完整 1632 道题库 — 无需注册。

Own the complete CSLB Law & Business guide — PDF + EPUB, $24.99 →

同考点相关题目

最近核对: · 审核流程

PrepPass 团队 · 依据官方资料核对 California CSLB Contractor License Law & Business Exam · 我们如何核对
审核人 Abraham Chen — Licensed California General Contractor (CSLB License #1101856 — 核实)
反馈