企业组织与执照第 1449 / 1632 题

Beyond the original application fee, an applicant must also pay which fee upon license issuance?

a.The initial license fee in the CSLB fee schedule
b.A renewal fee covering the first two-year license period
c.The annual premium on the $25,000 contractor's license bond
d.Nothing further, because the application fee covers issuance

解析

B&P §7137 sets the fee schedule, under which the applicant pays an application fee to be examined and a separate initial license fee before the license is issued; renewal fees start at the end of the first two-year cycle. (b) confuses the two: renewal comes later and is a different fee. (c) is not a CSLB fee at all — the bond premium is paid to a surety company, which is why it is not on the fee schedule. (d) is the misconception that one payment covers the whole process.

法律依据: B&P Code §7137

免费刷完整 1632 道题库 — 无需注册。

Own the complete CSLB Law & Business guide — PDF + EPUB, $24.99 →

同考点相关题目

最近核对: · 审核流程

PrepPass 团队 · 依据官方资料核对 California CSLB Contractor License Law & Business Exam · 我们如何核对
审核人 Abraham Chen — Licensed California General Contractor (CSLB License #1101856 — 核实)
反馈