Which element must a submitted HACCP plan spell out for every critical control point?
a.The retail price of the finished menu item at that step
b.The brand of thermometer purchased for that step
c.The method and frequency of monitoring at that step
d.The number of portions produced per hour at that step
解析
For each critical control point the plan identifies the significant hazards, the critical limits, the method and frequency of monitoring by the designated employee or person in charge, the action to take if a limit is not met, how the person in charge verifies the procedures are followed, and the records kept. Price, brand, and output are not part of that summary.
法律依据: FDA Food Code §8-201.14免费刷完整 500 道题库 — 无需注册。
Own the complete ServSafe Food Protection Manager guide — PDF + EPUB, $19.99 →
同考点相关题目
- A kitchen begins building a HACCP plan for its cook-chill soups. What is the first principle it must apply?
- In a HACCP plan for chicken salad, the team writes: cool from 135°F to 70°F within 2 hours. Which principle does that statement represent?
- A HACCP plan submitted to the regulatory authority must include a flow diagram. What must that diagram identify?
- A restaurant plans to add vinegar to its sushi rice specifically so the rice no longer needs temperature control. What does the Food Code require first?
- Which of these plans requires a variance from the regulatory authority before the operation may begin?
- A deli vacuum-packs cooked pork daily but removes every package from its wrapper within 48 hours. What does the Food Code allow?