Survey Planning
A quarter of the Engineering Surveying exam is about choosing the right method, equipment and control before any measurement is taken, and about what a civil engineer may and may not do under California law.
Scope of practice
The Professional Engineers Act defines civil engineering to include certain surveying, such as locating and establishing alignments and elevations for engineered works and topographic mapping (Business and Professions Code section 6731.1). Establishing property boundaries is land surveying under section 8726. A civil engineer registered before January 1, 1982 may practice land surveying (section 8731); others need a land surveyor license for boundary work.
Datums and coordinate systems
Horizontal positions in California are normally referred to the California Coordinate System of 1983, a set of six Lambert conformal conic zones, and elevations to a vertical datum such as NAVD 88. Grid distances differ from ground distances by the combined factor (the product of the scale factor and the elevation factor), and geodetic and grid azimuths differ by the convergence angle. Planning means deciding which datum the project needs and what control ties it down.
Choosing methods and accuracy
Match the method to the tolerance: differential leveling for precise elevations, trigonometric leveling or GNSS for topographic work, total station traverses or RTK for layout, photogrammetry or lidar for large-area mapping. Accuracy standards are expressed as a relative precision such as 1:10,000 or as a positional tolerance. Random errors are reduced by redundancy, systematic errors by procedure and calibration, and blunders by independent checks.