California Civil Engineer: Engineering Surveying Practice Test
Sample practice questions
A few real questions from this free bank, with full explanations. Use the practice tool above for the whole set.
- 1. Survey Planning
An angle is measured 4 times with the same instrument and procedure. The standard deviation of a single measurement is 4". What is the standard deviation of the mean?
- a.2.00"
- b.2.50"
- c.4.00"
- d.8.00"
Answer: a
Explanation: The standard error of the mean is sigma/sqrt(n) = 4/sqrt(4) = 2.00". Precision improves with the square root of the number of repetitions, not in direct proportion, so dividing by n (1.00") is too optimistic.
- 2. Survey Planning
Under the California Professional Engineers Act, which surveying task may a civil engineer licensed today (without a land surveyor license) perform?
- a.Establishing the property line between two privately owned residential lots
- b.Setting monuments at the lot corners of a newly recorded subdivision tract map
- c.Preparing and filing a record of survey that shows a retraced parcel boundary
- d.Determining ground contours and the position of fixed objects for a grading design
Answer: d
Explanation: Business and Professions Code section 6731.1 lets civil engineers do engineering surveying: topography, locating fixed works, and alignment or elevation for civil works. Establishing property lines, setting boundary monuments and filing records of survey are land surveying under section 8726 and need a land surveyor license (or a civil engineer registered before January 1, 1982).
- 3. Survey Planning
What does the term 'basis of bearings' on a set of plans tell the user?
- a.Which benchmark and elevation were held for all vertical work on the plans
- b.Which magnetic declination was applied to compass readings on the plans
- c.Which line and bearing were held to orient all other directions on the plans
- d.Which map scale was used to plot the bearings and distances on the plans
Answer: c
Explanation: The basis of bearings names the reference line (for example, between two control monuments) and the direction assigned to it. All other bearings are relative to it. The vertical equivalent is the benchmark statement, a separate note.
- 4. Field Data Collection
With a level telescope having a stadia interval factor of 100 and a stadia constant of zero, the upper and lower stadia hairs read 5.31 ft and 2.27 ft on a vertical rod held on a horizontal line of sight. What is the distance to the rod?
- a.152 ft
- b.304 ft
- c.379 ft
- d.608 ft
Answer: b
Explanation: Stadia distance = K x rod intercept = 100 x (5.31 - 2.27) = 304 ft. Averaging the two readings gives the center-hair rod reading, not an intercept, and halving the intercept has no basis for a horizontal sight.
- 5. Data Analysis and Evaluation
A simple horizontal curve has radius R = 800 ft and central (intersection) angle of 40°. What is the tangent distance T from the PC to the PI?
- a.232.94 ft
- b.273.62 ft
- c.279.25 ft
- d.291.18 ft
Answer: d
Explanation: T = R tan(I/2) = 800 x tan(20°) = 291.18 ft. Using the sine gives 273.62 ft, which is half the long chord, and using the full angle instead of the half angle gives 671.28 ft.
- 6. Data Analysis and Evaluation
A vertical curve 600 ft long connects grades of +3% and -2%. How far from the PVC is the high point of the curve?
- a.360.0 ft
- b.450.0 ft
- c.540.0 ft
- d.720.0 ft
Answer: a
Explanation: The high point is where the slope is zero: x = -g1 L/(g2 - g1) = -(3)(600)/(-2 - 3) = 360.0 ft from the PVC. It falls at midcurve only when the two grades are equal and opposite; here the turning point shifts toward the flatter grade.
- 7. Data Analysis and Evaluation
The azimuth of traverse line AB is 65°00'00". At B, the angle measured clockwise (angle to the right) from the backsight on A to the foresight on C is 110°30'00". What is the azimuth of BC?
- a.314°30'00"
- b.134°30'00"
- c.175°30'00"
- d.355°30'00"
Answer: d
Explanation: Azimuth BC = back azimuth of AB + angle to the right = (65°00'00" + 180°) + 110°30'00" = 355°30'00" (subtract 360° if the sum exceeds 360°). Adding the angle to the forward azimuth without the 180° reversal is the common error.
- 8. Mapping
Two spot elevations 50 ft apart on a uniform slope are 102.4 ft at point A and 107.8 ft at point B. How far from A does the 105-ft contour cross the line AB?
- a.0.5 ft
- b.19.3 ft
- c.24.1 ft
- d.25.9 ft
Answer: c
Explanation: Linear interpolation: distance = (contour - elevation A)/(elevation B - elevation A) x length = (105 - 102.4)/(107.8 - 102.4) x 50 = 24.1 ft from A. The value 25.9 ft is the distance measured from B instead.
- 9. Construction Surveying
A grade stake is set where the ground (top of hub) elevation is 104.62 ft. The design finished grade at that point is 101.30 ft. What should be marked on the stake?
- a.C 1.66
- b.F 3.32
- c.C 3.32
- d.F 6.64
Answer: c
Explanation: Cut or fill = hub elevation - design grade = 104.62 - 101.30 = +3.32 ft. The ground is above grade, so material must be removed: a cut of 3.32 ft. Reversing C and F is the costly mistake, since the contractor grades the wrong way.
- 10. Construction Surveying
Cut end areas at successive cross-sections spaced 100 ft apart are 210, 260, 190 sq ft. Using the average end area method, what is the total excavation volume?
- a.815 cu yd
- b.1,363 cu yd
- c.1,704 cu yd
- d.2,444 cu yd
Answer: c
Explanation: Sum the prisms between adjacent sections: V = L x sum[(Ai + Ai+1)/2] = 46,000 cu ft = 1,704 cu yd. Multiplying the sum of all areas by the spacing counts interior sections twice at full weight and end sections at full instead of half weight.