Repairs and Corrective Work
Branch 3 is the only branch that includes structural repairs and the correction of conditions. The field representative needs enough construction vocabulary to name the members involved, and must know when wood is replaced, when it may be reinforced, and how the cause is corrected.
The standard of work
Regulation 1937.14 requires all work to meet accepted trade standards for good and workmanlike construction and to comply with the building code in Title 24. If the inspector believes a building permit is needed, that is noted on the report.
Replace or reinforce
Structurally weakened members are replaced or reinforced. Fungus-damaged members may be reinforced instead of removed only where the wood is dry, meaning below 20 per cent moisture content, and the excessive moisture condition has been corrected. Surface fungus on sound wood may be treated or left once the moisture is corrected. A sister is a full-strength member fixed beside a weakened one and bearing on the same supports.
Naming the parts
The mudsill is anchored to the top of the foundation. Girders rest on posts and piers and carry the floor joists, which carry the subfloor. Cripple walls are short stud walls between foundation and floor. Studs frame the walls; rafters carry the roof; sheathing covers framing; the fascia runs across the rafter ends at the eave. Wood resting on concrete in ground contact is preservative-treated or naturally durable, and cut ends and drilled holes in treated wood are coated.
Correcting the cause
Lower the soil or raise the foundation to cure a faulty grade. Break earth-wood contacts by setting posts on concrete and separating fences and planters from the structure. Cut stucco back or lower the grade so the foundation is visible. Add or unblock vents, lay a vapour barrier, and correct drainage where the subarea is damp. Repair leaks at plumbing, showers and flashings before replacing the wood they damaged. Remove form boards and cellulose debris.
Who does the work and what follows
A Branch 3 company may do the repairs, or the owner may engage a licensed contractor: section 8556 lets licensed contractors remove and replace pest-damaged wood where the work is identified in an inspection report. Subcontracting does not relieve either company of responsibility. Branch 3 companies give the Notice to Owner about mechanics liens. After the work, the notice of work completed and not completed goes to the owner or agent within 10 business days, and a copy is kept three years.
How this area is tested
Questions describe damage and its cause and ask for the correction; choose the answer that stops the water or breaks the soil contact, not the one that covers the damage. Vocabulary questions ask you to name a member from its position. The 20 per cent moisture figure and the replace-or-reinforce rule appear regularly.