Reporting and Recordkeeping
Every Branch 3 inspection produces a written report on the Board's form, and the report drives everything that follows: the bid, the work, the completion notice and any certification. This area tests the contents of the report, the kinds of report, the deadlines, and the records the company keeps.
Deadlines to know
The report is delivered to the person who requested the inspection and to the owner or the owner's agent within 10 business days from the start of the inspection, and before any work begins. The address of the property is filed with the Board no later than 10 business days after the inspection begins or the work is completed; failure to file exposes the company to a fine of up to $2,500. Reports, field notes and activity forms are kept for three years and are produced to the Board within two business days of a demand. A report prepared for an attorney for litigation is exempt from filing.
What the report contains
Section 8516 lists the contents: the inspection date and the inspector's name; who ordered the report and who has an interest; the address; a general description of the building; a diagram showing where infestation, infection and conducive conditions were found, with the affected members named in ordinary construction terms; the conditions likely to lead to infestation; the bold statement on whether the exterior roof surface was inspected; the areas not inspected, with a recommendation for further inspection; the recommendations; the pesticide information required by section 8538; the reinspection terms; and the bold notice that the reader may seek a second opinion. Regulation 1990 adds the licence number and signature of the Branch 3 licensee who inspected.
Kinds of report
Regulation 1993 names them. An original report records the first inspection for a particular party or purpose, and is complete or limited. A limited report covers part of a structure, shows what was inspected, names who asked for the limitation and recommends further inspection of the whole. A supplemental report covers areas that were inaccessible and have been opened, or corrects an earlier report. A reinspection report records whether items on an original report have been completed. A reinspection is available only within four months of the original, costs no more than the original inspection, and is done within 10 business days of being ordered.
Separated reports
A separated report divides findings into Section I, visible evidence of active infestation or infection and the conditions that result, and Section II, conditions likely to lead to infestation or infection where none is visible. Areas that could not be inspected are listed as further inspection items. The company must tell the customer when the report is ordered that a separated report is available. Conducive conditions are never described as active infestations.
After the work
Within 10 business days after completing work the company gives the owner or agent a notice of work completed and not completed, stating the cost of the work done and the estimated cost of work not done. On request of the person who ordered the report, the company certifies under section 8519, in wording limited to evidence of active infestation or infection in the visible and accessible areas. A completion tag goes beside the inspection tag. Where a guarantee runs longer than three years, records are kept for the guarantee period plus one year.
How this area is tested
Most questions turn on a deadline, a document or a definition. Sort the numbers before the examination: 10 business days appears four times, two business days once, three years for records, four months for reinspection, five working days for a Branch 1 fumigation certification. Know which document does which job, and remember that a report is owed even when the inspection was free or the customer does not pay.
Keep going: the full California Structural Pest Control Field Representative — Branch 3 (Termite) guide covers every section of the exam. Branch 3 Field Representative Exam — California Termite Study Guide, 2027 Edition — PDF + EPUB, $14.99 · 14-day refund →

Practice stays free. The full California Structural Pest Control Field Representative — Branch 3 (Termite) study guide is the material itself, taught start to finish — a downloadable PDF + EPUB you keep.