1 questions

topics.ctnv_project_management

In a construction schedule, the critical path is best described as the path that:

  • a.Is the shortest route through the network
  • b.Carries the most float, giving the schedule flexibility
  • c.Has the fewest activities regardless of their durations
  • d.Is the longest chain of dependent activities, which sets the shortest possible completion time and has zero float

The critical path is the longest chain of dependent activities through the network. Because no other path is longer, it fixes the earliest the project can finish, and every activity on it has zero float, so any slip delays the whole project day for day.Construction Business & Law Manual for Nevada (CPM scheduling)

Report