The critical path in a project schedule is best described as the path that:

  • a.Carries the most float, giving the schedule flexibility
  • b.Is the shortest route through the network
  • c.Is the longest chain of dependent activities, has zero float, and sets the shortest possible completion time
  • d.Contains the fewest individual tasks

The critical path is the longest chain of dependent activities. Because no other path is longer, it fixes the earliest the project can finish, and every activity on it has zero float, so any slip pushes out completion day for day.CPM scheduling (critical path)

topics.ctsc_project_management

A South Carolina general contractor (GC-Building) wants to self-perform specialty trade work on its own project. Under CLB rules, this is generally allowed only when the specialty work is ancillary and does not exceed what share of the total project cost?

  • a.20%
  • b.50%
  • c.75%
  • d.100%

A South Carolina GC-Building contractor may self-perform specialty work only when it is ancillary to the building project and does not exceed about 20% of the total project cost; larger specialty scopes must be performed by an appropriately licensed contractor.S.C. CLB rule (GC-Building self-performed ancillary work)